INS11537 - Remission and insolvency proceedings

Minus remission

The decision to cancel a remission (or ‘un-remit’ by input of a ‘minus remission’) is taken by the Caseworker.

SA only

The Band E1 should

  • Access the SA screens to
  • View remissions and cancel the relevant items
  • Re-create the work items on IDMS
  • Update IDMS and SA Notes
  • Refer the case to the caseworker to consider the next action.

Mixed Heads of Duty

The Band E1 should

  • Prepare the appropriate form in the 164 series for the minus entries
  • Pass the case to the Band D or C2 to
  • Sign and authorise and then to pass the case back to the Band E1 to
  • Input the forms to send to the Control Team (deal with the remission on-screen if appropriate)
  • Note IDMS of the forms input
  • Note the SA record (if appropriate)
  • BF the case for three to four weeks and set Next Action (‘Caseworker review’) on IDMS
  • Note ‘AE’ on the front of the file with ‘BF (date)’. (Put on tasklist for three to four weeks to AE)

At the BF date the E1 should

  • Check the Head of Duty (HOD) and IDMS systems.

If minus remission is not shown on the HoDs

  • Take the necessary remedial action. (If an APS Network Unit (NU) charge then telephone the NU to deal with and update IDMS)
  • BF two weeks (Next Action: ‘Caseworker Review’ on IDMS).

If minus remission is shown on the HoDs

  • Refer the case to the caseworker to continue and consider the next action required.