ESM3190 - How to work out the deemed payment: transitional rules
Paragraph 22 Schedule 12 Finance Act 2000
Regulation 1(2) SI 2000 No.727
Although the size of the deemed payment depends upon amounts
received in a tax year, the legislation only has effect with
respect to income earned in respect of services performed on or
after 6 April 2000. Therefore amounts received by the intermediary
on or after 6 April 2000 in respect of work done before that date
should not be taken into account in working out a deemed payment.
Amounts received before 6 April 2000 for work done after that date
are treated as received in the 2000/01 tax year and taken into
account in working out the deemed payment for that period.
If an intermediary has a relevant engagement where some of
the services were performed before 6 April 2000 and some on or
after that date, then an apportionment should be made of the
income. This should be by reference to when the services to which
the income relates were performed. However, provided any
apportionment made seems reasonable, you should not spend a lot of
time trying to establish detailed figures.
Example
G Services Ltd has a contract under which it provides the
services of Mr G to a third party. The contract is a relevant
engagement and runs from 1 January 2000 to 30 September 2000. Under
the contract he has to work a five-day week for the client for
which the company is paid a daily rate. There is provision in the
contract for extra payments for overtime and weekend working. Over
the duration of the contract the company earns £28,950.
If the work was carried out evenly over the period of the
contract then it would be acceptable to apportion the income from
the contract on a time basis. This could be by reference to the
days prior to 6 April and on or after that date. However, if the
work was carried out on a more intermittent basis then it might be
necessary to make the apportionment by reference to the time
actually worked.
For example, although the contract ran from 1 January the
worker was only required on a part-time basis in the early stages
of the contract but had to work an extensive amount of weekend
overtime during the latter stages of the contract.
