| CISR43600 | Action guide contents |
From 6th April 2008 CIS will be able to recognise where four
consecutive monthly contractors returns have been not been received
by the due date from a contractor who also acts as a subcontractor
and holds gross payment status, and where the Scheduled Review (see
CISR49000) is not yet due. CIS will
initiate a process which will be run once a month to identify these
and run a system ‘ad-hoc’ TTQT to highlight these and
any other failures within the twelve month ‘qualifying
period’, and remove gross payment status from the
subcontractor.
A contractor record will not be examined for a system
‘ad-hoc’ TTQT until at least one month has passed since
the fourth consecutive monthly return penalty has been issued; this
is to take into account the possibility of any appeal being made by
the contractor against the penalties issued
The system ‘ad-hoc’ TTQT will be triggered where
CIS identifies four late consecutive contractor returns within the
period, which will be the current month minus 5 to the current
month minus 2. The date of the system ‘ad hoc’ TTQT
will be on the 7th day of each calendar month.
Example 1
| June 2010 return | Penalty issued 29th June 2010 |
| July 2010 return | Penalty issued 29th July 2010 |
| August 2010 return | Penalty issued 29th August 2010 |
| September 2010 return | Penalty issued 29th September 2010 |
| October 2010 return | Penalty issued 29th October 2010 |
| (Due date for the October 2010 return is the 19th October 2010) | |
On the 7th November 2010 CIS will look at the contractor returns
for June 2010 to September 2010, the penalty for the October 2010
contractors return will not be included as the 30 day appeal period
following the issue of the penalty will not yet have expired.
Where a first penalty has been issued in respect of four
consecutive contractor returns the system ‘ad-hoc’ TTQT
will run for the subcontractor
except where any of the following circumstances
are present:
The way that the system ‘ad-hoc’ TTQT will work is that CIS will look for the first penalty that has been issued in respect of the contractor’s return, and will count each first penalty issued in respect of that return. The system ‘ad-hoc’ TTQT will however ignore the following:
| June 2010 return | Return received after the due date |
| July 2010 return | Return received after the due date |
| August 2010 return | Return received after the due date |
| September 2010 return | Inactivity set |
| October 2010 return | Return received after the due date |
| November 2010 return | Return received after the due date |
| December 2010 return | Return received after the due date |
| January 2011 return | Return received after the due date |
The run of late contractor returns from June 2010 was
interrupted by the setting of Inactivity signal for the September
2010 contractor return, and so a new run commences from the October
2010 contractor return.
The system ‘ad-hoc’ TTQT will also work in the
same way that the normal ‘ad-hoc’ TTQT operates as
follows, so that:
Finally once the system ‘ad-hoc’ TTQT has run, CIS will then automatically set the date of the next Scheduled Review (see CISR49000). The subcontractor will be notified by the issue of a CIS308 regarding the loss of their gross tax treatment, and the implementation date for this change will be 90 days after the date of issue of the CIS308.