CISR14060 - The Scheme: construction operations: disputes about 'scope'
| CISR14600 | Action guide contents |
Under the Construction Industry Scheme these disputes generally take two forms
- the subcontractor objects to registering under the Scheme or to a deduction made by a contractor from a payment because they consider that the work done is outside the scope of CIS
- a contractor from whom deductions in respect of payments made are being sought by HMRC maintains that the work done was outside the scope of CIS
These situations are considered in the following paragraphs.
Subcontractor/Contractor dispute
Remember that the contractor is potentially liable to a penalty if they fail to verify and make a deduction in respect of a payment for construction work that is caught by the Scheme. For this reason the contractor's Processing Office should be responsible for the final decision on any dispute. Where there is a dispute between a subcontractor's/contractor's Processing Office and the contractor, you should obtain full details and any documentary evidence of the work carried out before referring to the CIS Advisory Team for guidance (see CISR97030).
Settling disputes - written confirmation
In the majority of cases, the question of whether or not a
particular operation falls within or outside the Scheme will be
relatively straightforward. In all cases you will need to obtain
precise details of the work to be carried out. This is essential in
the event that you are asked to confirm your decision in writing to
either, or both, parties to the contract. When doing so you should
always avoid generalisation and 'To whom it may concern' type
letters and only refer to specific operations carried out by the
subcontractor.
That said, disputes may still arise where a subcontractor
acknowledges that some work they do is within the scope of the
Scheme but claims that a particular contract is outside its scope
when payment is made. If such a dispute is referred to you, you
should consult the information panel at
CISR14050 and follow the action guide
at
CISR14610.
Contractor/HMRC dispute
Where a contractor is disputing their liability to account for a
deduction which it is believed should have been made from
subcontract payments, the contractor may contend that there was no
such liability because the work involved is not a construction
operation.
There is no procedure for laying a dispute between HMRC and
the contractor about the scope of the Scheme directly before the
Commissioners. Where such a dispute arises you should first try to
reach a settlement by agreement. If the contractor continues to
deny liability, you should then raise a Regulation 13 determination
covering the disputed deduction (for guidance about Regulation 13
determinations, see
CISR82000 onwards). The issue of the
determination gives the contractor the opportunity to appeal and
allows the matter in dispute to either go for an Internal Review,
or for a hearing before the Tribunal.
In these circumstances, follow the action guide at
CISR14620.
