CCM12276 - Opening and Working Enquiries: Avoiding Delay
You should do everything possible to minimise delays on your own
part as well as the claimant’s. If you need to consider
particularly involved or voluminous information, or if you are
waiting for information from a third party, some delay may be
inevitable. In these circumstances you should inform the
claimant(s) in writing that there is likely to be a delay, and tell
them the date by which you expect to be able to contact them again.
You should build in to your plans for working your cases, any
likely delays you can anticipate, for example annual leave, jury
service etc. You should avoid, if possible, setting a deadline for
the provision of information which coincides with the early stages
of your leave. Specify a date a week or two later than usual, if
appropriate, and make a note on TCW to explain why you have done so
(see TCW Guidance).
There will of course be some delays you could not have
anticipated - for example, if you need to take sick or special
leave lasting more than a few days. In this event, it will be your
manager’s responsibility to take steps to maintain progress
on the case by applying whatever measures are necessary.
Every effort must be made to ensure that enquiries are worked
without unreasonable delay. Unreasonable delays can have an impact
on interest charges and the imposition of penalties. If there has
been a delay and a penalty position has been established the CCO
should consult their manager to consider whether the delay is
unreasonable due to the extent that a penalty should not be sought.
If the manager is uncertain about this they should contact their
CCGM for advice.
