PSA6050 - Using the Employer Compliance System for PSAs

Updating ECS when you Vary a PSA

PSA2070 explains how to make changes to a PSA. The action you must take to update ECS will depend on the reason why the charge is being amended

To include a new item

  • click on the ‘Add’ button

To exclude an item

  • Click on the ‘Withdraw’ button

In both cases

  • Select the relevant item and make required changes to the date
  • Click on ‘OK’

If a charge is increased a new reference is created and the previous reference is deleted

  • enter the new reference on the new P630
  • make a note of the previous reference in ECS ‘Notes’

To amend a charge

  • click on ‘Charge’
  • amend the entries
  • enter the new settlement date