PAYE Month 8 - period ending 5th December 2007
Electronic payment due 22nd December 2007
PAYE Month 8 - period ending 5th December 2007. If you pay electronically HMRC must receive your payment by 22nd of the month. But as the 22nd December 2007 is a non-banking day, we must receive cleared funds no later than Friday 21st December 2007.
The last day for initiating payment is therefore -
Wednesday 19 December if you pay by telephone or Internet banking, BACS
Direct Credit, Bank Giro or Alliance & Leicester Commercial Bank,
or by Friday 21st December if you pay by CHAPS.
Please note that the above dates are only shown as a guide. Your bank
or building society may take longer to process the payment, and will have
a cut-off time for initiating a payment on a particular day. You will
have to contact your bank or building society to see when your payment
should be made.
Further payment information can be found at 'How to pay PAYE'.