Construction Industry Scheme Operational Forum (CISOF) - Minutes
Tuesday 30 September 2008, New Nelson Room, New Wing, Somerset House, London
Attendees:
HMRC
Roy Massingale - [RM] (Chair)
Ray Bourley - [RB]
Ken Claydon - [KC]
Jeremy Croucher - [JC]
Peter Grattidge - [PG]
Dot Bartlett - [DB]
Terry Dummett - [TD]
Industry
Jim Etherton - [JE] BASDA
Liz Bridge - [LB] CC
George Northall - [GN] CBI
Sue Cave - [SC] FSB
Tim Cross - [TC] JTC
Eric Rolfe - [EC] JTC
Gordon Marjoram - [GM] FMB
Howard Royse - [HR] ICAEW
Stephen Burrell - [SB] CIOT
Elaine Gibson - [EG] (IPP)
Apologies
Suzanne Nichol
Maurice Denyer
Ken Tracey
1. Minutes of last meeting and action points
The minutes were agreed
Action point 1 - KC reported that there was plenty
of guidance available to cover what happens to penalties once a company
has notified HMRC that it has ceased. Action closed.
Action point 2 - The CIS helpline doesn't
currently maintain a record of frequently asked questions. An impromptu
one was undertaken at KC's request but revealed no surprises. Scope
for discussion here with the helpline for an FAQ's register to be
developed for the future. [New action point 1 - KC will take
this forward]
Action point 3 - see agenda item 2e) below
Action point 4 - An update to the CIS website covering
advice that Contractors re-verify when a delay in the issue of a form CIS316A
is at point is to be published today. Apologies given for the delay -
this due to a misunderstanding by the HMRC web publishers. Action closed.
Action point 5 - RB said that no records were kept
of 'reasonable excuses' given in individual cases. However, DB had undertaken
a sample during visits to Network offices. Common reasons were cashflow,
illness, ignorance of the new scheme, agents, domestic problems, postage
problems. Action closed.
Action point 6 - see agenda item 2d) below
Action point 7 - RM took forward anecdotal suggestion
of delays in being able to get through to the CIS helpline to senior managers.
There were some delays at the tax credits renewals time when staff were
temporarily redeployed to cover what was perceived to be a more crucial
area. However RM has stressed that the industry also relies on the helpline
for its livelihood and cannot afford to have staff redeployed from it at
any time. CIS is different to other contact centres/helplines. KC reported
that everything was back to normal and in w/c 22nd September, the average
response rate was 96 per cent in 20 seconds with 100 per cent of all calls
answered. Action closed.
Action point 8 - KC reported that there had been
a backlog of 720 stuck verification cases at the time of the last CIRIP
meeting in July. However this had now fallen to 60, which is the usual weekly
quota. All affected contractors had been contacted. New cases were identified
automatically. Only affects online verification and is not a common problem.
Action closed.
Action point 9 - KC said that It was possible (although
very rare) for partners in a partnership to have different tax treatments.
No further guidance needed. Action closed.
Action point 10 - covered by post-meeting note
of 23 July (see page 8 of the CIRIP information pack for 30 September 2008).
Action closed.
2. HMRC Issues
(a) future arrangements
- RB said that Bob Cope had stepped down from CIRIP and ACCA had not
as yet named a replacement. Bob had made a very valuable contribution
to CIRIP over many years and his contribution would be missed.
- Due to a refurbishment programme at Bush House, the next CIRIP meeting
would be on Thursday 20 November in Room 73, 2nd Floor, New Wing, Somerset
House. Members may need to wait in reception. And (regrettably) there
will be no refreshments.
- For the New Year onwards RB suggested that CIRIP meetings should be
held on a quarterly basis. Industry side agreed. Dates would be notified
in due course for 2009. In view of this, any particular industry issues/concerns
in between meetings should be emailed to Jeremy
Croucher.
- RM suggested that as the implementation stage of CIS was over there
should be a new name for the panel.
(b) CIS stats
- RB apologised for the late arrival of CIRIP information packs. The
statistical information had only arrived from our statisticians, who were
under pressure in the run up to PBR, on the morning of 29 September.
- There were some glitches in the stats provided, notably the graph on
page 11 of the information packs - headed 'Penalty Appeals
(to September)'. The figures shown in the graph were incorrect but
HMRC will discuss with its statisticians and get this rectified for the
next meeting.
- RB said that the levels of returns and penalties appeared to have reached
a settled level.
- The May, June and July 2007 penalties issued in August 2008 (graph
on page 13 and 14 of the packs) were due to late notifications by contractors
who should have been in the scheme throughout.
- LB has seen a case where tax has been accounted for and paid each month
but returns have not been filed, resulting eventually not only in a lot
of returns to complete but a lot of penalties for late filing. KC pointed
out that HMRC did not know what CIS tax was coming in on a month-by-month
basis due to the making of single tax payments. RB suggested that the
UTRs of any known problem cases should be fed back for investigation as
to what has happened.
- DMB are now taking action to chase some of the contractors who continue
to get penalties month-on-month.
- GM wondered if there was any evidence to suggest improved compliance
once a penalty was imposed. HR would like to see stats on the yield from
penalties and how much HMRC is actually collecting. RB agreed to put penalties
and in particular an update of the DMB action on the agenda for the next
meeting.
- LB raised concern over the very tight timeframe for completion of the
monthly return. If there was evidence to suggest that the 15 per cent
of the contractor population missing the filing date were only doing so
by a small margin, was this not reason for considering an extension of
the completion timeframe to (say) three weeks?
- RB said that there was a regular pattern of returns coming in over
the post-filing dates of each month, although it was difficult to know
whether all those received at the end of the month related to that month.
Online filers represented a very small percentage of late filers.
(c) TTQT
- RB said that the September TTQT stats showed the failure rate at 28
per cent, the same as it had been for a number of months. There was a
current backlog in cases awaiting review but steps were being taken to
reduce this.
- RB pointed out that TTQT stats were a snapshot of the position at a
point in time showing the numbers which had been fully reviewed (automated
and manually) and the proportion which had ultimately failed (taking into
account successful appeals)
- GN will provide details of a case that seems to have bypassed the automated
process - one where TTQT resulted in a failure notice but, on appeal,
no failures could be found on the CIS record.
- SC expressed concern over what guidance was provided for helpline advisors
where nothing seemed to be happening with a GPS application made.
- SB expressed concern over what appeals guidance was given to local
offices. HMRC said that generic guidance was provided but that ultimately
it was for a local office to decide what is or is not a reasonable excuse
in individual cases. There was no requirement for local offices to escalate
cases to the Head Office CIS team.
- Suggestion made that the website includes specific guidance on what
to do when a payment can't be made (for example, because of cashflow
problems). KC suggested that this guidance already existed on the Employers'/PAYE
website. RM said that the broader issue of time to pay and recovery policy
was outside the CIS team's remit. However, he would seek some clarification
on the point from DMB and try to get a DMB representative to attend the
next meeting to cover the issue.
(d) Scope
- RB advised that little progress had been made.
- The exclusion of carpet fitting was the subject of a 1981 Statement
of Practice based on legal advice provided at the time. He had not yet
been able to locate this legal advice. If it could not be located shortly,
the next step would be to seek further advice from our solicitors.
- HR asked what guidance there was about the CIS position of 'buy-to-let'
investors. RB pointed out that the distinction for CIS had always been
between passive investment, where the only expenditure was to maintain
the fabric of the property - in which case the investor would need
to be spending more that £1 million a year to be in CIS -
and the developer who would demolish, or materially alter, the property
who would be regarded as a mainstream contractor.
(e) Compliance
- By way of some background to his new role, PG explained that compliance
activity in the department is changing. This is mainly due to the number
of people working in the department.
- RISK will become more and more of a consideration in the future.
- Currently compliance activity in construction impacts many areas. Typical:
- Large Business Service (LBS) - who deal with the top 50 companies
controlled by Client Relations Managers (CRMs)
- Local Compliance - divided into customer groups of Large and Complex
(some dealt with similarly by CRMs), Small and Medium, Cross Cutting
groups (the bulk of CIS and Construction Industry Team (CIT) work, and
Targeted Education, Enabling & Leverage (TEEL) teams (who will be
dealing with straightforward cases)
- Special Compliance Investigations (SCI) - high profile fraud
cases.
- What are we doing now to help our customers?
- Relying on RISK to identify review cases
- Looking to refine this by creating two specialist risk teams focusing
on construction (centralised RISK teams prepare packs)
- We want to focus on those who are non-compliant (not those who are)
- Next major aim is for 'one-stop-shop' reviews.. These will
be cross-cutting embracing CT, ITSA, VAT, CIS, PAYE etc.
- Looking for elimination of duplication (all encompassing 'real
time' visits).
- Employment status needs more focus going forward.
- Consistency with penalty regime (Powers review)
- Staff reductions still needed, together with a reduction in the number
of office locations
- Published Departmental Services Objectives will apply concentrating
on the reduction in the tax gap and the improvement of customer service.
- Compliance statistics for PY and PY-1 show:
- 2006-07
- Compliance reviews concluded - 4,191
- Cases where employment status incorrectly applied - 748
- Yield from status reviews - £17,164,246
- 2007-08
- Compliance reviews concluded - 7,262
- Cases where employment status incorrectly applied - 550
- Yield from status reviews - £17,684,320
- LB raised a concern that the industry does not seem to be using the
ESI tool very much. [New Action Point 2 - JC to establish
where we are with ESI and circulate to CIRIP]
- TEEL service is currently available to offer services to new contractors
(for example, on status considerations) [New Action Point 3 -
PG will report at next meeting how TTEL access is obtained]
- 'Open an early dialogue' is a current initiative. This is designed
to reduce the burdens on business where a review is being conducted.
- JTC could be a source to pursue here (ie provision of own RISK rules).
- Addressing Action Point 3 (see agenda item (1) above),
PG summarised that the thought process behind the action was to see if
there were ways of following money through CIS and then using this information
to profile cases to take up for compliance review. [New Action
Point 4 - PG will prepare a more informed view on this for discussion
at the next meeting]
3. Industry Issues
Rosa Tormo had emailed JC on 25 September expressing concern about another
HMRC 'CIS' forum about which CIRIP had heard nothing.
RB advised that this was a three-series forum set up to look at employment
and false self-employment, the final meeting of which had been held on 27
September. It was not a CIS forum. The meetings were fact-finding in nature
designed to flesh out some of the detail and the nature of relationships/arrangements
etc. CBI had been represented at the meetings.
CIRIP was the only CIS forum.
4. AOB
- JE asked what had become of the CIRIP wish list for future enhancements
to CIS. RM said that this would be put on the next agenda.
- ER enquired as to the correct position with regard to verification
numbers. He'll pass specific details to KC to pursue and advise.
- SB asked if consideration could be given to the segregation of CIS
and other remittances.
- KC drew attention to the CIS factsheet series. These were introduced
in the implementation period of the new scheme. They have not been either
revised or reprinted but have been available since in PDF format. All
of the issues contained are now addressed on dedicated pages on the CIS
website so agreement sought to formally drop the factsheets. Agreed.
- Next meeting - Thursday 20 November 2008 - 10.30
am - Room 73, 2nd Floor, New Wing, Somerset House. JC will
circulate formal invites in due course. Items for the agenda under 'Industry
Issues' need to be emailed to JC by close of business on Wednesday
12 November.